Scoring Purpose

The TriSeadon points matrix provides a single, auditable scoring system for yard operators and contractors across GOGO, GOCO, and COCO participation tracks.

Contractor Control Baseline

Ships and new-tech baselines | Cost and governance controls

What Performance Points Control

Points create consequences inside the funded program; they do not appropriate money. A strong score earns priority among qualified sources and supports exercise of authorized options, additional workshare, future competitions, and yard opportunities. A poor score triggers corrective action, work withdrawal, or operator replacement.

Program continuity is judged separately at the fleet level. When independently verified need, affordability, delivery, quality, industrial-capacity, cleanup, workforce, and ROI gates remain satisfied, the Navy carries a minimum viable TriSeadon rate in its program and budget submission. Congress retains the decision to authorize and appropriate funds.

Open Earned Program Continuity

Points Bands

Cost, schedule, quality, module delivery, and training are scored as separate ledger entries. Points accumulate across the program, with graduated consequences at +50, -50, -75, -100, and -125. A contractor cannot use an early or inexpensive delivery to erase a quality failure on the same event.

Hull Cost Score

Score Condition Measurement Rule
+10 Final accepted hull cost is more than 5% below the authorized target Scope, quantity, and acceptance requirements must remain unchanged
0 Final accepted hull cost is from 5% under through 3% over target In-budget tolerance band
-10 Final accepted hull cost is more than 3% over target Corrective cost analysis required

Hull Schedule Score

Score Condition Class Delivery Gate
+10 Accepted at or before the early-delivery incentive gate FFG 20 months; DDG 38 months; CAG 48 months
0 Accepted after the incentive gate but no more than 9 calendar days after the contractual delivery date FFG 24 months; DDG 48 months; CAG 60 months
-10 Accepted 10 or more calendar days after the contractual delivery date Schedule-cause and recovery review required

Baseline protection: scoring uses the government-approved target cost, scope, and contractual delivery date after signed change orders. Government-caused delay, directed scope growth, force majeure, or an approved supply-continuity exception does not count against the contractor. A contractor cannot earn underrun or early-delivery points by deleting scope, deferring defects, moving unfinished work past acceptance, or using an unapproved baseline change.

Hull Quality Score

Hull Final-Acceptance Credit

Certified Module and Equipment-Package Scores

A scoring unit is one complete, serialized, contract-defined package that passes its required DLA and USN acceptance gates. Contractors may not split internal components, consoles, pumps, or subassemblies into extra scoring events. A clean module can earn no more than +15: +5 for final acceptance, +5 for early delivery, and +5 for delivery more than 5% under budget.

Qualifying Deliverables

CategoryPositiveNeutralNegative
Final acceptance+5 after complete DLA/USN acceptance0 while incomplete, conditionally delivered, or awaiting acceptanceNo delivery penalty by itself; cost, schedule, QA, and compliance entries remain separate
Cost+5 when more than 5% under target after acceptance0 from 5% under through 3% over-10 when more than 3% over target
Schedule+5 when at least 20% ahead of the contractual duration0 through the contractual date and 9-day grace period-10 when 10 or more calendar days late
QualityNo separate positive score; final acceptance provides the +5 completion credit0 when accepted without a scored rejection-5 for failed acceptance or scored rework, with further enforcement for an unresolved defect

Examples: an accepted module that is both early and more than 5% under budget earns +15. An accepted module that is both late and more than 3% over budget scores +5 -10 -10 = -15 before any separate QA or compliance penalty.

A module QA failure may post an additional -5 if it remains unresolved after 90 days or causes a shipyard critical-path delay. Acceptance points and final payment are not released until DLA and Navy acceptance records are complete.

Cross-Training Credits

Training credits are intentionally smaller than hull and module execution scores. They act as constant national modifiers that reward a yard for sending people out, receiving students, and keeping qualified teams in circulation across the country.

Threshold Rules

Due-process and emergency rule: point thresholds do not replace federal suspension, debarment, safety, fraud, cybersecurity, environmental, labor, or national-security authorities. Those authorities may require immediate protective action before a numerical threshold is reached. Conversely, removal or reassignment must preserve worker safety, evidence, government property, technical records, and fleet-production continuity.

Quarterly Ledger Audit

The cumulative point ledger governs the +50, -50, -75, -100, and -125 actions. A quarterly Vendor Performance Score remains a management dashboard for diagnosing why the ledger is moving, but it does not replace or override posted points.

Quarterly Review Bands
  • Green (>= 90): no dashboard-level corrective action; point-threshold rules still govern priority.
  • Yellow (80-89): management review and corrective-action tracking; no automatic point change.
  • Red (< 80): focused audit and cure-plan review; allocation changes occur only when the cumulative ledger or a separate safety/legal authority triggers them.

Carrots and Sticks (Execution Clauses)

Contracting discipline: no engineering-change insertion after first steel cut unless safety/security or supply continuity exception is certified.

Where It Is Used

Continue in Order