Program Decision Lock (Current Plan)

TriSeadon expands the naval industrial base through four linked layers at the same time: 3 new major GOCO yards, modernization of the existing GOGO/Navy-run yards including Hawaii, expansion support for existing COCO/private yards, and a 50-state module-campus network that fabricates parts, modules, and long-lead systems for final assembly at the major waterfront yards.

Why this structure is used: major yards handle erection, combat-system integration, test, commissioning, and deep refit, while the distributed network builds subassemblies, missile-support parts, modules, and common technologies so the large yards do not become a single bottleneck.

1) Assumptions and Yard-Cost Drivers

Open the full ship-cost and tonnage comparison in Cost

2) Construction Timing, Yard Flow, and DLA Support

Open Logistics Line | Open Build and Refit Schedule

3) Ship-Cost Comparison Lives in Cost

The detailed tonnage, historical analog, current U.S. comparator, and TriSeadon recurring-cost comparison has been consolidated into the Cost page so affordability stays in one place.

Open Ship Cost and Comparative Summary

5) Shipyard Network from Expansion Document

A. National capital GOCO yards (3 total, ~$5B each)
  • Mandatory per major GOCO yard: 1 CAG build drydock and 2 medium build drydocks (medium docks are dual-qualified for FFG or DDG).
  • Mare Island, CA: 1 large build drydock + 2 large build piers (3 CAG lanes), 2 medium build drydocks + 6 medium build piers (6 DDG/FFG lanes), and 1 large refit dock.
  • Sparrows Point, MD: 1 large build drydock + 2 large build piers (3 CAG lanes), 2 medium build drydocks + 6 medium build piers (6 DDG/FFG lanes), and 1 large refit dock.
  • Brownsville, TX: 1 large build drydock + 2 large build piers (3 CAG lanes), 2 medium build drydocks + 6 medium build piers (6 DDG/FFG lanes), and 1 large refit dock.
  • GOCO-major subtotal (3 yards): 3 large build drydocks + 6 large build piers (9 CAG lanes), 6 medium build drydocks + 18 medium build piers (18 DDG/FFG lanes), and 3 large refit docks.

GoCo Yard Costs Sheet (Major Yards)

Budget baseline is fixed at $5B all-in per major GOCO yard for site control, clearing, remediation, and full buildout into revenue-generating federal assets.

Cost Element (Per Major GOCO Yard) Percent Cost (USD)
Environmental remediation + shoreline reclamation10%$0.50B
Training center + workforce housing/facilities10%$0.50B
Core lane buildout (1 large CAG lane + 2 medium DDG/FFG lanes, docks, piers, cranes, heavy utilities)60%$3.00B
Labs, shops, mission-support buildings, security, digital controls, and commissioning reserve20%$1.00B
Total CapEx Per Major GOCO Yard100%$5.00B

Major GOCO program total (3 yards): $15.0B CapEx.

Lifecycle Sustainment Sheet (Annual, Per Major Yard)

Lifecycle Sustainment Element Annual Cost Range (USD)
Facilities maintenance workforce + contracted maintenance$120M-$180M
Lifecycle recapitalization reserve (docks, cranes, utilities, systems)$80M-$140M
Environmental compliance, monitoring, and continuing cleanup$40M-$90M
Utilities, base operations, and security$60M-$110M
Total Annual Sustainment Per Major Yard$300M-$520M

Annual sustainment for 3 major GOCO yards: $0.9B-$1.56B/year.

  • Lifecycle planning model: permanent facilities staff (Sandia-style), asset management, and recapitalization scheduling to avoid deferred maintenance risk.
  • Cleanup planning baseline: average ~1 acre/year across program life, with annual variation based on regulatory approvals, sequencing, and shoreline restoration windows.
  • Funding mix: shipyard modernization accounts, yard expansion appropriations, environmental cleanup appropriations (eligible scope), and direct federal capital for strategic infrastructure.
  • Economic framing: these outlays purchase long-life federal production assets that continue generating capacity and lease-revenue offsets over decades.
B. Regional GOCO yards (superseded in current plan)
  • Planning note: this regional GOCO concept is retained for historical continuity only and is not part of the active funding baseline.
  • Radio Island, Morehead City, NC: 1 medium build drydock + 2 medium build piers (3 DDG/FFG lanes), plus 1 medium refit lane.
  • Port Tampa Bay, FL: 1 medium build drydock + 2 medium build piers (3 DDG/FFG lanes), plus 1 medium refit lane.
  • Regional GOCO subtotal (2 yards): 2 medium build drydocks + 4 medium build piers (6 DDG/FFG lanes), and 2 medium refit lanes.
  • Marinette, WI is treated in this site baseline as a COCO/private Great Lakes yard with DLA storage linkage.
C. Legacy Navy yards (Navy-run direct federal spend)
  • Norfolk, VA: 1 full CAG-capable large lane envelope plus medium DDG/FFG build and refit support.
  • Portsmouth, ME: no new-build lane in baseline; kept as overhaul/surge support in this phase.
  • Puget Sound, WA: 1 full CAG-capable large lane envelope plus medium DDG/FFG build and refit support.
  • Pearl Harbor, HI: refit-only and sustainment support with 1 large CAG-capable refit dock and 2 pier spots minimum so the yard can service all three classes.
  • Legacy subtotal (capacity posture): 2 CAG-capable large lane envelopes (Norfolk and Puget), overhaul/surge support at Portsmouth, and one large refit-only position at Pearl Harbor.
  • Active cost line: $4B total (4 x $1B across Norfolk, Portsmouth, Puget, and Pearl Harbor).

GoGo Yard Costs Sheet (Current 4 Navy-Run Yards)

Funding baseline for this plan is $1.0B per existing GoGo yard (4 yards total = $4.0B). This is treated as direct federal infrastructure spend with mission-readiness return rather than lease-income return, and it is specifically structured so TriSeadon work does not interrupt existing submarine, carrier, overhaul, decommissioning, or other sovereign yard missions.

Allocation Category (Per GoGo Yard) Percent Amount (USD)
Environmental cleanup and remediation10%$100M
Training center and temporary workforce housing10%$100M
TriSeadon ship-lane buildout in underused or recoverable yard areas (1 large lane, 1 drydock, 3 pier spots, and core labs/shops)50%$500M
Current-yard mission modernization (CVN, SSN, nuclear/decommissioning support, and core mission sustainment)25%$250M
Total Per GoGo Yard100%$1.0B

4-yard GoGo total: $4.0B federal spend.

  • Strategic framing: unlike GOCO, this line is not expected to generate direct lease revenue; return is readiness, mission continuity, national industrial resilience, and the lowest recurring cost per completed hull.
  • Protected mission rule: existing submarine, carrier, overhaul, decommissioning, and other sovereign work keeps priority. TriSeadon lanes, shops, training, and housing are added in underused areas so the current yard mission is not interrupted.
  • Cash-influx rule: the added funds are used across the yard for hazmat cleanup and reclamation, training and housing, new TriSeadon lane buildout, and modernization of legacy mission spaces.
  • Lane utilization rule: each new TriSeadon lane is structured for staged parallel flow, with up to four hulls occupying different construction stages at one time.
D. Private yards (loan-assisted expansion)
  • Marinette, WI is included in the COCO/private lane set in current site continuity.
  • 10 COCO/private sites remain in the network as competitive expansion capacity: at least one floating medium opening (1 drydock + 2 piers = 3 lanes) can be assigned to COCO and rotated by workload, repair burden, weather, or readiness demand, but the baseline program does not depend on COCO alone to meet schedule.
  • Cost line: ~$500M each, ~$5B total.
  • Funding line (active baseline): up to $500M per yard at 3 percent program rate over 20 years, with a Year-1 no-payment startup window and availability covenants; single-lane refit-only sites receive a reduced loan package.

COCO Yard Loan Cost Sheet

Eligible COCO/private yards may receive up to $500M in federal loan support at a 3% program rate over 20 years, with no payment due in Year 1, contingent on mandatory allocation and lane-availability covenants.

Loan Allocation Requirement (Per COCO Yard Loan) Minimum Percent Amount at $500M Loan Cap (USD)
Environmental cleanup/remediation scope10%$50M
Training center support and temporary housing10%$50M
TriSeadon shipbuilding lane buildout (convert existing line or construct new line)35%$175M
Modernization/equipment/operations integration scope45%$225M
Total100%$500M
  • Minimum delivery covenant: each funded yard must stand up at least one TriSeadon-capable shipbuilding lane.
  • Lane-access covenant: the funded TriSeadon lane must remain open and available for TriSeadon production for the full duration of the open loan.
  • Non-compliance trigger: lane closure or unavailability during loan term is treated as covenant breach and triggers federal remedy/penalty actions defined in loan agreements.
E. State module campuses (state partnership model)
  • Active baseline: all 50 states are offered a state module-campus pathway (primary + alternate candidates), with opt-in timing controlled by each state and multi-site growth allowed where justified.
  • Products: ISO pods, berthing nodes, Cerberus mounts.
  • Funding line: up to about $150M state contribution matched by up to about $150M federal contribution for the core campus package, with additional help available through hazmat, learning, union, VA, and similar grant programs.
  • Campus form: the simple uniform default is a two-yard campus with two 100-acre yard cells sharing one backbone, but the model remains flexible from one yard to four yards where regional conditions require it.
  • Recovery line: state and federal shares split contractor lease/rent streams for the first 10 years, or until the initial public capital is recovered; after that the state receives 100% of lease/rent streams and the 200-acre campus is released to the state with hazmat reclamation complete.

6) DLA Supply Chain Model

DLA On-Demand and Just-in-Time Delivery Workflow
  1. Module campus receives demand guidance from DLA based on ship starts, refits, reserve goals, and forecasted consumption.
  2. The campus draws approved materials and components through DLA channels or the qualified civilian counterpart lane tied to the same baseline.
  3. The campus fabricates the certified module (IWM, IMM, ISO, or subsystem package) under TriSeadon interface and quality standards.
  4. The finished module goes through DLA acceptance for fit, configuration, quality, and documentation.
  5. Once accepted, payment is released and contractor points are posted to the producing yard or team.
  6. DLA either stages the accepted module in its distribution/storage network as strategic reserve or routes it just in time to the yard most likely to use it next.
  7. When a GOCO, GOGO, or COCO shipyard hits the required build or refit milestone, DLA issues the module and the shipyard installs it into the hull.

Operating logic: DLA and the civilian counterpart lane feed the inputs, module campuses build to baseline, DLA accepts the finished module for payment and scoring, and then DLA either stores or delivers that module according to real fleet demand.

DLA Current Footprint (Official Baseline)

CONUS (17):

  • Albany, GA
  • Anniston, AL
  • Barstow, CA
  • Cherry Point, NC
  • Corpus Christi, TX
  • Hill, UT
  • Jacksonville, FL
  • Norfolk, VA
  • Oklahoma City, OK
  • Puget Sound, WA
  • Red River, TX
  • Richmond, VA
  • San Diego, CA
  • San Joaquin (Tracy), CA
  • Susquehanna, PA
  • Tobyhanna, PA
  • Warner Robins, GA

OCONUS (7):

  • Bahrain
  • Europe (Germersheim)
  • Guam
  • Korea
  • Pearl Harbor, HI
  • Sigonella, Italy
  • Yokosuka, Japan

7) Financial Picture

8) Expansion Timeline Phases

8A) Lane Reconciliation (Current Chronology Demand)

Allocation by yard groups: GOCO major = core large-hull and medium-hull build throughput; legacy = CAG-capable large-lane envelopes at Norfolk and Puget plus sovereign overhaul/surge support at Portsmouth and large refit-only coverage at Pearl Harbor; COCO/private yards (including Marinette lane capacity) provide rotating floating openings, optional single-lane refit support, and surge or foreign-sales expansion above the core baseline. The controlling rule is that build lanes can absorb refit work in war or disruption, but dedicated refit lanes are not assumed to generate equivalent new-build throughput.

9) Continuity and Governance Notes

9B) GOCO Vendor Model and National Growth Rules

9A) Risk and Mitigation Clause Set (GoGo and COCO)

Objective: make participation practical, auditable, and enforceable while protecting mission readiness and taxpayer value.

GoGo Yard Clause Set (Navy-run yards)
  • Milestone disbursement rule: release funding in gated tranches (design complete, permit complete, civil works complete, lane certified, operations accepted).
  • Protected mission rule: CVN/SSN/decommissioning workload has pre-defined priority windows; TriSeadon lane work cannot force unsafe mission deferral.
  • Allocation audit rule: environmental, training/housing, lane buildout, and mission modernization percentages are auditable and reported quarterly.
  • Lane throughput rule: each funded lane is certified for staged multi-hull flow with explicit safety and quality gates before throughput expansion.
  • Lifecycle sustainment rule: annual facilities maintenance staffing and recap reserve are mandatory to prevent deferred-maintenance collapse.
  • Exception rule: national emergency, major casualty, or regulator stop-work events can trigger temporary lane reallocation with documented recovery plan.
COCO Yard Clause Set (Loan-supported private yards)
  • Loan covenant rule: TriSeadon-capable funded lane must remain open and contract-available while loan is outstanding.
  • Availability definition: "open and available" means staffed, certified, and schedulable within contracted lead-time windows.
  • Idle-capacity treatment: if federal program demand is below committed minimums, partial standby compensation may apply under pre-agreed terms.
  • Breach remedy rule: unauthorized closure or inaccessibility triggers cure period, rate step-up, clawback, and potential acceleration/default actions.
  • Performance incentive rule: early delivery, quality, and cost-performance scores improve access to future loan rounds and workshare priority.
  • Transfer/control rule: ownership or control changes require federal consent to preserve lane covenant continuity through full loan term.
Cross-Cutting Program Safety and Feasibility Controls
  • Independent engineering validation before each major phase release.
  • Integrated master schedule with permit-critical path and long-lead procurement buffers.
  • Workforce realism gate: funding release linked to verified hiring/training pipeline readiness.
  • Environmental compliance gate: no phase advance without cleanup milestone closure and regulator concurrence.
  • Industrial resiliency gate: dual-source plans for critical systems to avoid single-vendor lock risk.
  • Program transparency: quarterly public scorecard for cost, schedule, quality, and lane availability.

10) Full Extract (Complete Document Coverage)

Note: The extract below preserves original document wording for audit traceability. Where extract figures differ, the controlling baseline for this site is the Program Decision Lock above (4-yard GOGO allocation lock, 3-yard GOCO $5B lock, COCO 10/15/35 allocation lock, and 1% state-note recovery model).

Open full extracted text from TriSeadon Shipyard expansion.docx
1. Assumptions (Post–Industrial Base Build-Out)
	•	FFG: 500 ft OAL × 66 ft beam × approximately 10,000 tons
	•	DDG: 650 ft OAL × 88 ft beam × approximately 15,000 tons
	•	CAG: 800 ft OAL × 108 ft beam × approximately 32,000 tons
Cost Drivers
	•	Yard efficiency gains:
	•	GOCO model = reduced profit margins (lease revenue substitutes some profit).
	•	Legacy yards = lowest cost (time + materials only).
	•	Private yards = slightly higher, but offset by loan assistance.
	•	DLA bulk buys: –10 to –15% per hull (steel, turbines, radars, VLS, pods).
	•	ISO & Node yards: Pre-outfitting cuts labor ~8–10%.
	•	Standardization across classes: Shared IMMs, IWMs, Cerberus mounts, radars, powerplants = reduced design churn.

2. Construction Time per Class
	•	FFG:
	•	Legacy US builds: ~36 months.
	•	TriSeadon modular method: 24 months per hull (parallel outfitting, JIT supply).
	•	DDG:
	•	Legacy Arleigh Burke Flight III: ~72 months.
	•	TriSeadon: 48 months per hull (fewer design changes, larger yards, modular inserts).
	•	CAG:
	•	Comparable to CGN/large CVN auxiliaries (5+ years historically).
	•	TriSeadon: 60 months per hull (standardized heavy-lift modules, fewer bespoke systems).

3. Cost per Ship (2025–2035 $ Estimates)
Baseline: Current U.S. Programs
	•	FFG-62: ~$1.4–1.6B each (and slipping higher).
	•	DDG-51 Flight III: ~$2.2–2.5B each.
	•	CG/large combatants: ~$6–7B if built today.
TriSeadon Adjusted Costs
	•	FFG: ~$1.25B → $1.0–1.1B each
	•	Savings: DLA steel bulk buy ($50–70M), GOCO/legacy margin cut (~$50–100M).
	•	DDG: ~$2.5B → $2.0–2.2B each
	•	Savings: Bulk VLS buys ($100–150M), standardized radar/powerplant (~$100M).
	•	CAG: ~$6B → $4.5–5.0B each
	•	Savings: Scale on steel & power ($250–300M), module standardization (~$200M).

4. Comparative Summary
Class
Displacement
Build Time
Legacy Cost (est.)
TriSeadon Cost
% Savings
FFG
~7,500t
24 mo
$1.4–1.6B
$1.0–1.1B
20–30%
DDG
~15,000t
48 mo
$2.2–2.5B
$2.0–2.2B
10–15%
CAG
~32,000t
60 mo
$6–7B
$4.5–5.0B
20–25%

✅ Bottom Line
	•	FFGs: Big winners — TriSeadon beats the troubled FFG-62 program by ~$400–600M per hull and delivers 1/3 faster.
	•	DDGs: Slightly cheaper but much faster — cutting 2 years off build cycle keeps fleet numbers up.
	•	CAGs: Still expensive, but $1.5–2B cheaper than comparable legacy cruisers; standardized modules make sustainment easier.
The real gain isn’t just per-hull cost but throughput: with parallel lanes, ISO nodes, and DLA buffers, the Navy avoids bottlenecks that have plagued every major program since the Cold War.


A. National “Capital” GOCO Yards (2 total, $5B each)
1. Mare Island, Vallejo, CA (West Coast)
	•	Ownership: Former Navy shipyard (federal land, much of it transferred to Vallejo but could potentially be re-acquired by federal action, purchase or land swap and congressional approval). 
	•	Footprint: ~1,400 acres (ample for 3 graving docks, 5 slipways, 5 piers, large module halls, storage).
	•	Infrastructure: Legacy drydock basins already exist, though major modernization required; deep-water access via San Pablo Bay.
	•	Capacity: 1 × Large (CAG) build lane, 1 × large refit dock, 2 × Medium (DDG/FFG) build lanes.
	•	Workforce: Bay Area + Central Valley, legacy shipyard labor pool, strong regional tech base.
	•	Investment: ~$5B modernization to create a full capital yard and cover Brownfield cleanup.
	•	Risk: Requires re-acquisition from City of Vallejo (political and legal complexity).
	•	Pros: Historic Navy site, proven deepwater, potential flagship yard west of Mississippi.
2. Port of Brownsville, TX (Gulf Coast)
	•	Ownership: ~40,000 acres controlled by Port of Brownsville (public navigation district).
	•	Candidate Parcel: ~302 acres currently marketed for industrial/maritime use (unpriced, but likely $15M–$60M based on comps).
	•	Infrastructure: 17-mile channel, ~42 ft draft (authorized deepening to 52 ft), on-dock rail, barge and truck access.
	•	Capacity: 1 × CAG build lane, 1 × large refit dock, 2 × Medium (DDG/FFG) build lanes.
	•	Investment: ~$5B for graving docks, Goliath cranes, module halls, logistics facilities. Hurricane hardening (N+1 power, onsite gen, surge protections
	•	Pros: Massive publicly owned port land; deepwater access; large labor pool from Gulf Coast ship/energy industries.
	•	Cons: Politically sensitive to repurpose land from a thriving commercial port; would require federal–state negotiation or federally driven reallocation.

B. Regional GOCO Yards (3 total, $3B each, except Marinette at $1B)
3. Marinette, WI (Great Lakes)
	•	Ownership: Formerly federal (BRAC); now operated by Fincantieri Marinette Marine. Could potentially be re-acquired via negotiated settlement.
	•	Footprint: ~300 acres, proven DDG/FFG new construction yard.
	•	Capacity: 2 × Medium (DDG/FFG) build lanes, 1 × medium refit.
	•	Investment: ~$1B for modernization into modular GOCO.
	•	Pros: Experienced shipbuilding workforce, existing infrastructure.
	•	Cons: Currently under private control—would require federal reacquisition.
	•	Possible replacements if Fincantieri won’t settle: NCBC Gulfport MS, Lake Charles, LA
4. Radio Island, Morehead City, NC (East Coast)
	•	Ownership: ~154 acres state-owned under NC Ports (within a 200-acre port complex). Expandable via dredge fill.
	•	Depth: 45–47 ft channel at Beaufort Inlet, no air-draft limits.
	•	Capacity: 2 × Medium (DDG/FFG) build lanes, 1 × medium refit, ISO/module support.
	•	Investment: ~$3B for slips, drydocks, and module halls.
	•	Workforce: Eastern NC labor pool (Onslow, Craven, Pitt Counties); strong pipeline from MCAS Cherry Point (≈3,800+ civilians/military) and Camp Lejeune (≈6,000+ civilians) for skilled trades.
	•	Pros: Public/state-controlled land; fewer existing conflicts than Charleston.
	•	Cons: Requires cooperation from NC Ports and state government; some dredging/land reclamation needed.
5. Port Tampa Bay, FL (Southeast)
	•	Ownership: Hillsborough County Port Authority (public).
	•	Footprint: ~1,000 acres industrial land, with parcels suitable for 250+ acres dedicated to shipyard. (portoftampa.com)
	•	Depth: 43 ft today, with federal project to deepen to ~47 ft under way. (portoftampa.com)
	•	Capacity: 2 × Medium (DDG/FFG) build lanes, 1 × Medium (DDG/FFG) refit, ample space for ISO/module shops and logistics staging.
	•	Workforce: Tampa/St. Petersburg metro area (~3.2M population) provides a large, relatively untapped industrial and veteran workforce.
	•	Pros: Public ownership (no private eminent domain); major port with planned deepening; large workforce outside existing Navy shipbuilding hubs.
	•	Cons: Shared with commercial and cruise shipping—would need careful site selection and coordination to avoid disruption.


1. National Shipyard Expansion
A. New GOCO Capital Yards (Flagships – $5B each)
Mare Island Vallejo CA & Brownsville Tx
	•	Land: Former Navy/industrial bases; re-aquired under federal control.
	•	Lanes:
	•	1 × Large (CAG/DDG/FFG) build
	•	1 × Large refit (CAG/DDG/FFG)
	•	2 × Medium (DDG/FFG) build
	•	Cranes: 600-ton Goliaths at each lane
	•	Cost: $5B each.
	•	Timeline: 2026–2032.
	•	ROI: 2–3% lease = $100–150M/yr per yard (perpetual lease income).
	•	Governance: Navy retains control; vendors lease lanes. Performance points system: on-time/under budget = +points (expand contracts); late/over budget = –points (risk replacement).

B. New GOCO Regional Yards ($3B each, Marinette $1B)
Tampa Bay FL, Radio Island NC, Marinette (WI)
	•	Land:
	•	Tampa Bay/ Radio Island: State Port Authority/DoD property.
	•	Marinette: transferred from Fincantieri under forfeiture settlement (yard acquired free; Navy invests $1B modernization).
	•	Lanes:
	•	2 × Medium (DDG/FFG) build
	•	1 × Medium refit (DDG/FFG)
	•	Cranes: 600-ton Goliaths per lane.
	•	Cost: $3B each (Charleston, Ingleside); $1B (Marinette).
	•	Timeline: 2026–2031.
	•	ROI: $60–90M/yr lease per yard.
	•	Governance: Same performance point system as capital GOCO yards.

C. Legacy Navy Yards (Navy-Run, Direct Federal Spend)
Norfolk (VA), Portsmouth (ME), Puget Sound (WA), Pearl Harbor (HI)
	•	Lanes:
	•	Norfolk: 1x Full CAG-Capable Large Lane + Medium Throughput Support
	•	Portsmouth: 1x Medium Build (DDG/FFG)
	•	Puget Sound: 1x Full CAG-Capable Large Lane + Medium Throughput Support
	•	Pearl Harbor: 1x Medium Build (DDG/FFG) + refit support
	•	Cranes: 600-ton Goliaths per lane.
	•	Cost: 4 × $1B = $4B.
	•	Timeline: 2027–2035.
	•	ROI: No income, lowest cost hulls (time + materials, no margin) overtime ROI.
	•	Strategic Role: Baseline comparison for GOCO/private yards; training pipelines; nuclear/CVN/SSN sustainment.

D. Private Yards (Loan-Assisted Expansion)
	•	Sites: 10 (Gulf, Great Lakes, East, West) — excluding DDG-51 program yards.
	•	Lanes: 1x Medium (DDG/FFG) build and/or 1x Medium (DDG/FFG) refit lane with 1x 600t crane.
	•	Cost: $500M each = $5B total.
	•	Funding: 1% fixed federal loans, repayment begins after first hull.
	•	Timeline: 2027–2035.
	•	ROI: Net-neutral — ~$5.75B repaid on $5B loans.
	•	Strategic Role: Widens base, creates control factors to measure against GOCO/legacy performance, uses skilled contractors to set training and skills for other yards.

E. ISO & Module Yards (State Partnerships)
	•	Sites: 20 across 20 states.
	•	Scale: 5–20 acre facilities.
	•	Products: ISO pods, berthing nodes, Cerberus CIWS mounts
	•	Cranes: Container cranes/forklifts only.
	•	Cost: $250M each = $5B total.
	•	50/50 split: $2.5B federal loan @2% + $2.5B state/local.
	•	Timeline: 2026–2030.
	•	ROI: Loan fully repaid (~$2.9B). States keep jobs; federal cost ~0.
	•	Strategic Role: Expands political footprint to 20+ states; keeps module supply distributed.

2. Defense Logistics Agency (DLA) Supply Chain Model
A. Central Procurement
	•	DLA = single buyer of steel, engines, turbines, radars, VLS, batteries, IMMs, IWMs, Odyssey pods, Cerberus CIWS, DEW.
	•	Buys 10–20 shipsets at a time; reduces cost 10–15%.
	•	Steel requires new domestic naval-grade mills (Midwest/South). Federal loans finance upgrades.
B. Depots & Logistics
	•	4 regional depots:
	•	East Coast (Norfolk/Philly)
	•	Gulf Coast (Mobile/Ingalls)
	•	West Coast (SF Bay Area)
	•	Midwest (Great Lakes/Marinette)
	•	Store shipsets, modules, ISOs; deliver JIT to yards.
C. Strategic Inventory Doctrine
	•	Baseline: 10 FFG + 8 DDG + 3 CAG shipsets (21 ships), plus a separately calculated rotating repair and refit float.
	•	Golden Rule: If inventory vs build conflicts → build wins. No yard sits idle.
	•	Scale-up:
	•	2026–30: 2–3 FFG + 1–2 DDG sets.
	•	2030–35: 5 FFG + 5 DDG + 2 CAG.
	•	2035+: steady 10/10/4 floor.
D. Funding
	•	2026–30: $3–4B (steel mill loans, depot builds, turbine contracts).
	•	2030+: $1.5–2.5B annually (sustain reserves + active builds).
	•	Steel mill loans repaid at 2–3%.

3. Financial Picture
Category
Sites
Cost
ROI/Repayments
Net Federal Impact
New GOCO Flagships
2
$10B
$200–300M/yr lease
$10B
New GOCO Regionals
3
$7B
$180–270M/yr lease
$7B
Legacy Navy Yards
5
$6B
None (cheapest hulls)
$6B
Private Yards
10
$5B loans
~$5.75B repaid
≈0
ISO/Module Yards
20
$2.5B fed loans + $2.5B states
~$2.9B repaid
≈0
Steel Mills & Depots
—
$3–4B loans
Repaid at 2–3%
≈0
Gross Federal Outlay: ~$31–32B
Repayments: ~$11–12B
Net Federal Cost: ~$19–21B over 6–8 years
Ongoing Lease ROI: ~$380–570M/yr (GOCO yards)

4. Timeline (Phases)
	•	2026–2029: Marinette online (2 FFG lanes). ISO yards in first 10 states. Tampa/Radio construction.
	•	2028–2032: Mare Island, Sparrows Point, and Brownsville (GoCo heavy build/refit) phase online. Tampa/Radio DDG lanes open. First legacy yards (VA, ME, WA) online.
	•	2030–2035: Pearl Harbor DDG/FFG lane active with refit support. All ISO yards finished. Private yard expansions complete.
	•	2035+: Full national capacity online: ~14 DDG/FFG buildways, 10 DDG/FFG drydocks, 2–3 CAG docks, 17 fit-out berths. Steady state: 8 FFG/yr, 6 DDG/yr, 2 CAG/yr + parallel refits.

✅ Why This Works
	•	Control: GOCO yards federally owned — Navy can swap out poor performers without losing capacity.
	•	Performance Management: Lease point system enforces accountability (On-Time/On-Budget = rewarded; late/over = penalized).
	•	Redundancy & Competition: 5 GOCO, 5 Navy-run, 10 private = three comparative streams; prevents bottlenecks.
	•	5 new GoCo shipyards are in new workforce areas providing untapped labor options.
	•	Resilience: DLA keeps 21 shipsets in reserve plus a rotating repair/refit float, but prioritizes throughput (no idle yards).
	•	Steel Security: Federal loans ensure U.S. naval steel capacity expands without taxpayer-owned mills.
	•	Politics: 25–30 states benefit via GOCO, legacy, private, and ISO yards.
	•	Redundancy in case of vendor failure, weather, war access to multiple shipyards to continue building refitting ships throughout the TriSeadon program.
	•	Affordability: Net Federal spend ~$20B, easily absorbed by Navy’s $40–47B annual shipbuilding budget.
	•	Return: GOCO yards generate ~$400–600M/yr lease income; legacy yards lower per-hull costs; private/ISO/state campuses repay loans.

          

Continue in Order