Reviewed August 2026

Use

Ratings are preliminary. Program leadership must assign accountable owners, quantitative thresholds, review dates, and closure evidence before authorization. A fallback preserves a buildable fleet when an objective system is delayed.

RiskCategoryProbabilityConsequenceLeading indicatorMitigationFallbackDecision authorityReview date
Requirements growthAcquisitionHighCriticalChanges after baseline lockConfiguration board and funded blocksDefer changeProgram executiveQuarterly
Baseline instabilityEngineeringHighCriticalUnclosed requirements at PDRInterface and baseline freezePause authorizationNavy technical authorityEach design review
Cost underestimationFinancialHighCriticalIndependent estimate varianceCAPE, CBO, and Navy estimatesRescope or rephaseMilestone decision authorityAnnual
Yard activation delayIndustrialHighHighPermits or construction miss critical pathWave activation and alternate sitesShift starts to ready yardsIndustrial program leadMonthly
Workforce shortagesWorkforceHighHighVacancy or attrition threshold exceededPortable credentials and staged hiringShift modules or cadenceWorkforce leadQuarterly
Supply-chain concentrationLogisticsHighCriticalSole-source or lead-time alertSecond sources and strategic inventoryCertified substituteDLA and Navy supply leadMonthly
Module-interface failureEngineeringHighHighReference module fails fit or testDigital thread and physical qualificationFixed installationInterface authorityEach certification
Software integrationTechnicalHighCriticalLand-site regression or cyber test failureIncremental releases and land integrationFielded baselineCombat-system authorityEach release
Mk 57 PVLS missile certificationWeaponsHighHighWeapon qualification slipsEarly certification and production planMk 41 VLS IWMWeapons authorityQuarterly
APM availabilityWeaponsHighHighLauncher or payload schedule slipIndependent large-payload laneDefer payloadWeapons authorityQuarterly
Pod qualificationPropulsionHighCriticalHydrodynamic, acoustic, shock, or endurance failureFull qualification programShaft and rudderPropulsion authorityEach test gate
Battery safetyPowerHighCriticalThermal event or containment failureContainment, ventilation, suppression, certificationReduced battery roleElectrical and safety authoritiesEach test gate
Trinion developmentWeaponsHighCriticalRecoil, cost, accuracy, or ammunition failureIncremental land test and cost gateMk 45 Mod 4 or certified gunWeapons authorityEach test gate
Sensor integrationCombat systemsMediumCriticalPower, cooling, EMI, or track-quality shortfallLand-based and shipset integrationCertified baseline fitCombat-system authorityEach design review
Excessive topside weightNaval architectureMediumCriticalKG or service-life margin breachedWeight control and independent stability reviewRemove deferred payloadChief naval architectMonthly
Cooling marginPowerHighHighMission profile exceeds heat-rejection marginZonal cooling model and growth reserveLimit simultaneous loadsElectrical authorityEach design review
Acoustic performanceASWMediumHighMeasured signature misses objectiveModel, isolate, and conduct full-scale trialsMachinery or propulsor correctionASW authorityTrial gates
Schedule concurrencyAcquisitionHighCriticalConstruction begins before design/test maturityEntry criteria and schedule-risk analysisDelay startMilestone decision authorityBefore each start
State participation shortfallIndustrialMediumHighMatch or site commitments lapseWave competition and alternatesReallocate campusIndustrial program leadEach wave
Environmental cleanup delayEnvironmentalHighHighUnknown plume, liability, or permit delayEarly characterization and phased constructionAlternate parcelFederal environmental leadMonthly
DLA inventory costLogisticsHighHighObsolescence or carrying cost exceeds planDemand signals and controlled reserve levelsSlow or redirect productionDLA program leadQuarterly
Governance fragmentationGovernanceMediumCriticalConflicting waivers or authoritiesSingle configuration authority and oversightPause expansionService acquisition executiveQuarterly

Risk Heat Map | Readiness Matrix | Lessons Learned